Re: Can a cost center be changed on a framework PO

$
0
0

Hi Ramin,

 

First of all thanks for the reply. Actually my PM asked me to change the cost center on framework PO.I block the original line item then add the line and enter GL code & new cost center but after saving the PO its back to original cost center. Any idea or I need to open new PO.

 

Thanks,

Zain