Dependent Demand Distribution

$
0
0

Dear PPDS experts,

 

I am facing problem with distribution key . I have updated the Distribution key GLEI (Equal distribution) in Production version and the same has been updated in the BOM component. When I run product Heuristics in the PPDS system is creating one planned order in APO and Respective dependent demand. When that Planned order moved to ECC system, because of the Distribution key it is splitting the order quantity in the planned order duration equally, but it is not splitting the dependent demand of the Component.

 

I would like to know is there any prerequisites/ settings for the component to the dependent demand split. Your suggestions are highly appreciated.

 

Regards

Prabhakar Reddy