Hi,

 

To clarify your request, there is a mistake in your scheduling information.

 

If you have two operations for 1M and 3M, when you schedule the plan, first order will be created with only 1M (operation1), second will be 1M (operation 2) and third will be 1M&3M combined or merged (based on strategy hierarchy)

 

In this case, if your strategy hierarchy for 1M and 3M is same, system will generate two orders, unless the order is TECO, another order will not be generated.

 

If your strategy hierarchy is different for 1M and 3M, then system will generate only one order, so if you CNF or PCNF, system will not consider. It will consider if the order is TECO and schedule the next call.

 

Regards

Terence