Re: Activate Integrated Planning for Cost Line Items posting

Hi Sanjeev,

 

 

Many thanks for your help. Sorry for not replying sooner but I did not have access to SAP system during this period of time.

 

 

What do you mean when you suggest me to check project controlling version? A transaction code would be helpful.

 

 

When I use CJR2 to upload plan amounts, I enter the version 1. Which parameter should I change? In my previous post I detailed the parameters for this CO Version.

 

I select in CJR2 the layout to enter data by WBS Element/Cost Element/Activity type. I guess this answers to the question of which is my type of cost planning.

 

I have checked the values on SAP CO tables:

-Table COEP is not being updated.

-However, COSS and COBK are being updated.

-RPSCO is being updated for the period that I modify (for example, if I change value in period 4, it updates fields WLP04 and WTP04).

 

 

I would appreciate if you could provide me with further help to my issue.

 

 

Many thanks and best regards,

 

 

Pablo